AD Ports to invest in Kazakh port

Under the deal, AD Ports Group owns 51% stake.

PIF acquires stake in Saudi Re

The acquisition was made by way of a capital increase.

ADNOC Gas awards contracts

The $2.1bn contracts are aimed at enhancing LNG supply infrastructure.

ADNOC L&S buys stake in Navig8

The company will acquire the remaining stake in mid-2027.

DAE to acquire Nordic Aviation Capital

The terms of the transaction have not been disclosed.

Bahrain invites bids for BIA Cargo Express Village project

  • The work includes the construction, testing, and commissioning of Phase 1-A of the Cargo Express Village
  • Bids will be open to only Grade A and Grade AA building contractors registered with the Bahrain’s Ministry of Works

Authorities in Bahrain have invited bids for construction work pertaining to the Cargo Express Village at the Bahrain International Airport, said local reports on Sunday, August 8.

The request for proposal has come from the Bahrain Airport Company, with the deadline for submitting the bids being September 12, said the reports.

The work reportedly includes the construction, testing, and commissioning of Phase 1-A of the Cargo Express Village.

The key facilities being planned include a warehouses zone spread over a 12,500-sq-m area, two power substations, a landside access road from Al Rayya highway, and a car-parking zone and security guard house at the entrance of the Cargo Express Village.

This, the reports said, is in addition to water tanks, a pumping station, and an emergency gate.

Zone A is expected to have a 5,000-sq-m warehouse facility exclusively for logistics group FedEx in addition to other storage facilities spread over 7,500 sq m.

BAC said the scope of work as part of the project would also include an airside security wall with associated works, an emergency gate, airside roads and a yard.

According to the Tender Board, bids will be open to only Grade A and Grade AA building contractors registered with the Bahrain’s Ministry of Works.